Shift summary
--------------
09:30 : Hall B started calo calibration. No Beam during 30 min.
10:20 : Beam is back 1uA.
10:45 : Beam is off.
11:37 : Beam is back 4uA.
12:33 : TWOARM runs. Didn't succed to move the target, so continued to take production data
13:27 : Bleedthrough = 0.9%
Run list:
---------
run 4945 : Production good run (300k)
run 4946 : Production good run (300k)
run 4947 : Production good run (300k)
run 4948 : Pedestals
run 4949 : Production good run (300k)
run 4950 : Production good run (300k)
run 4951 : twoarm
run 4952 : Production good run (300k)
Nb trips:
----------
08:00 - 09:00 : 14
09:00 - 10:00 : 7
10:00 - 11:00 : 5
11:00 - 12:00 : 8
12:00 - 13:00 : 13
13:00 - 14:00 : 13
14:00 - 15:00 : 14