Hall A Experiment #: e01015
01/08/05 0000-0800
Shift Leader: Peter Monaghan
Shift Workers: TO: Aidan Kelleher , 3rd: Eli Piasetsky
0000 | 0100 | 0200 | 0300 | 0400 | 0500 | 0600 | 0700 | Total Time | |
---|---|---|---|---|---|---|---|---|---|
Acceptable Beam in Use | 0.00 | 0.00 | 0.00 | 0.00 | 0.50 | 0.75 | 0.87 | 0.75 | 2.87 |
Beam Available but Not in Use | 0.00 | 0.00 | 0.00 | 0.00 | 0.25 | 0.08 | 0.00 | 0.17 | 0.50 |
Beam Not Available or Unacceptable | 1.00 | 1.00 | 1.00 | 1.00 | 0.25 | 0.17 | 0.13 | 0.08 | 4.63 |
Accelerator Con- figuration Change | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
Experiment Ready | 1.00 | 1.00 | 1.00 | 1.00 | 0.75 | 0.92 | 1.00 | 0.92 | 7.58 |
Planned Config- uration Change | 0.00 | 0.00 | 0.00 | 0.00 | 0.08 | 0.08 | 0.00 | 0.08 | 0.25 |
Unplanned Experiment Down | 0.00 | 0.00 | 0.00 | 0.00 | 0.17 | 0.00 | 0.00 | 0.00 | 0.17 |
Hall not ready reasons | |||||||||
Target | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
Data Acq | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
Other | 0.00 | 0.00 | 0.00 | 0.00 | 0.17 | 0.00 | 0.00 | 0.00 | 0.17 |
HRSL | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
HRSR | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
HALL_OFF | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
Comments: Problems with Moeller quadrupoles. Proceeded with 5uA cw beam and tested our daq, magnet steering and tried to take some data. Lost a little time in 4am hour as the fileserver crashed again.
Data Entry by: Peter Monaghan