14:03 start shift with run 1606
( 4cm LD2 with 2*2 raster ) at 34uA .
17:54 end of run 1606 (300 k) .
17:55 Called MCC to increase the current to 40uA.
17:56 start run 1607 (200 k) .
19:00 start run 1608 (200k ) .
20:05 start run 1809 .
20:10 MCC called.
They have problem to deliver the beam (FSD problem ).It might take 10min .
20:14 Beam Back .
20:28 MCC called again. FSD problem and no beam in the Hall.
20:56 Beam back .
21:15 Beam keeps tripping off due 2KW FSD faults. MCC still working to fix this problem.
21:55 run 1809 ended at 130k because ROC5 was not responding.
22:09 Fixed the problem of ROC5 by rebooting the trigger supervisor (both ROC5 and trigger supervisor seems to be connected together).
22:11 start run 1810 (200 k) .
23:14 start run 1811 .
23:57 run 1811 still running.