Hall A Experiment #: e01015
03/15/05 0800-1600
Shift Leader: W. Boeglin
Shift Workers: R. Miachels, R. Gilman
0800 | 0900 | 1000 | 1100 | 1200 | 1300 | 1400 | 1500 | Total Time | |
---|---|---|---|---|---|---|---|---|---|
Acceptable Beam in Use | 0.67 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.25 | 0.58 | 1.50 |
Beam Available but Not in Use | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.42 | 0.42 |
Beam Not Available or Unacceptable | 0.33 | 1.00 | 1.00 | 1.00 | 1.00 | 1.00 | 0.75 | 0.00 | 6.08 |
Accelerator Con- figuration Change | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
Experiment Ready | 1.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.92 | 0.58 | 2.50 |
Planned Config- uration Change | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
Unplanned Experiment Down | 0.00 | 1.00 | 1.00 | 1.00 | 1.00 | 1.00 | 0.08 | 0.42 | 5.50 |
Hall not ready reasons | |||||||||
Target | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
Data Acq | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.08 | 0.00 | 0.08 |
Other | 0.00 | 1.00 | 1.00 | 1.00 | 1.00 | 1.00 | 0.00 | 0.00 | 5.00 |
HRSL | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.42 | 0.42 |
HRSR | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
HALL_OFF | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
Comments: Beam Studies -> Hall in Controlled access Problem with TDC in S2m L
Data Entry by: W. Boeglin