    Log entry time 06:54:05 on June 02, 2005

    Entry number 144898

    This entry is a followup to: 144897

    keyword=Shift/ beam steering summary

    MCC asked us to do the beam steering at 4-pass, or 3.651 GeV.

    At 185 amps, the right septum steered the beam a tick mark left on the beam dump viewer. RHRS Q1 did little. The left septum (at 185 A) brought the beam back to center. LHRS Q1 did little.

    The dump ion chambers did not read anything at the 1 uA CW used for the steering study.

    MCC called in Arne Freyburger for a test plan, after which they will go to 2-pass setup for the hall.