User name R. Michaels
Log entry time 14:51:28 on June 8,2005
Entry number 145555
This entry is a followup to: 145508
Followups:
keyword=Trigger time adjustment
Adjusted the "ctime" overlap (see halog 145508) by increasing
1st channel of Ldelay1 in trigger map by 16 nsec. To compensate
for this and preserve relative timing of T3 to T5, I decreased
the 5th channel of Ldelay by 16 nsec. Downloaded the trigger.
Should be good to go... but we didn't take access (accelerator
division needs the beam) and therefore I didn't check on a scope.