User name R. Feuerbach
Log entry time 16:13:26 on June 16, 2005
Entry number 146224
keyword=Plan for this evening
The magnet power supplies are still under repair, so E94-107
still cannot take production data. The technical crew will stop
working at 8pm tonight, at which point the Hall will be swept and
locked up in preparation for beam.
So, by 9pm the hall should be ready to receive beam. The
activities for tonight are:
9pm Calibration of the SLI (Arne Freyberger) (1hr)
-> Arne, please call the Counting House when you are
finished.
10pm Calibration of the nA cavities (~3hrs)
(B.Michaels, J.Musson, L.Kaufman)
~2am Effects of shielding on Detector rates (4hrs)
(B.Wojtsekhowski, N.Liyanage)
6am Beam delivery to the hall will cease, and a request for the
Hall to be surveyed in preparation to going to Restricted
Access for the day shift to continue repairs.
The SWING and OWL shifts are ACTIVE to ensure shift coverage
during this time.
If you have any questions, please contact the Run Coordinator at
867-1787.