User name E.Chudakov
Log entry time 00:01:37 on June28,2005
Entry number 147298
keyword=Shift summary
Crew: E.Chudakov, N.Lianage, P.Pamela
16:00 Status: control access to fix vacuum problems in the chicane area.
18:25 We asked for beam permit.
19:10 CW beam in the hall (C target, 5µA)
19:20 55 µA, production start
20:10 MCC: the Moller quads are off. Started to investigate.
20:40 We resumed production with the quads off (it seems OK)
21:40 Beam is taken away to tune Hall C
23:25 Beam is back
run target comment
4921 C-thin short run to check the raster
4922 H2O 1M wrong prescaling factors (a lot of T1...)
4223 same 0.4M MCC noticed that the Moller quads were OFF! run stopped.
4926 same 1M production (Moller quads off)
4927 same 0.08M - run stopped since MCC took the beam away
4928 same - running -