    Log entry time 00:14:46 on October 14, 2005

    Entry number 156762

    keyword=Beam Time Accounting
    Hall A

    10/13/05 1600-2400
    Experiment #: E99-115
    Shift Leader: E. Burtin
    Shift Workers: K. Slifer, A. Acha

    16001700180019002000210022002300Total Time
    Acceptable Beam
    in Use
    0.000.000.000.000.000.000.000.000.00
    Beam Available
    but Not in Use
    0.000.000.000.000.000.000.000.000.00
    Beam Not Available
    or Unacceptable
    0.000.000.000.000.000.000.000.000.00
    Accelerator Con-
    figuration Change
    1.001.001.001.001.001.001.001.008.00
    Experiment
    Ready
    1.001.001.001.001.001.001.001.008.00
    Planned Config-
    uration Change
    0.000.000.000.000.000.000.000.000.00
    Unplanned
    Experiment Down
    0.000.000.000.000.000.000.000.000.00
    Hall not
    ready reasons
    Target0.000.000.000.000.000.000.000.000.00
    Data Acq0.000.000.000.000.000.000.000.000.00
    Other0.000.000.000.000.000.000.000.000.00
    HRSL0.000.000.000.000.000.000.000.000.00
    HRSR0.000.000.000.000.000.000.000.000.00
    HALL_OFF0.000.000.000.000.000.000.000.000.00

    Comments: 16:30 beam in the hall for optics optimization and compton tune. 17: 50 harp scans in the arc to check beam size

    Data Entry by: E. Burtin