• Main INDEX
  • Monthly INDEX
  • PREV
  • NEXT

    User name jpchen

    Log entry time 16:02:26 on October17,2005

    Entry number 157219

    keyword=day shift summary

    Day shift:
    SJ: J. P. Chen, TO: X. Qian, 3rd: J. LeRose.

    8:00 production
    8:05 beam current fluctuation, asked MCC to look into.
    A laser lock problem.
    8:20 requested controlled access to fix the right dipole problem.
    8:40 Hall A in controlled access, Ed/Mark/Heidi went into the hall.
    12:05 MCC put hall to power permit.
    12:20 to beam permit.
    12:22 Talked to techs, turned out they just went to lunch. The work in the hall is not done (still trying to figure out the cause of the problem for the right dipole). Back to controlled access.
    16:00 still in controlled access.

    Run 5697, 7:22-8:18, 100K events, 30K OK pairs. Left arm only.
    run 5698,5699,5700,5701, pedestal runs.