Shift Summary:
----------------
08:00 Waiting for right dipole to ramp
08:30 Mott measurement started (no beam for hall)
11:00 Mott completed and backed out. Hall B laser not locked -- beam down while injector group works. See other halog entries on B-laser bleed through issue.
Polarization: ~86%
15:30 MCC/Injector group had several problems getting B-laser lock back and restoring beam. First good production beam this shift.
Happex Run Summary:
-------------------
5930: JUNK (negligible beam) Production Run with only Left, Right Arm Septum Ramping Up.
5931: Production run (both arms)
Compton Run Summary:
12351: started 15:30