    Log entry time 16:03:42 on November 14, 2005

    Entry number 160179

    keyword=Beam Time Accounting
    Hall A

    11/14/05 1100-1600
    Experiment #: E99-115
    Shift Leader: Higinbotham
    Shift Workers: Lindgren , Qian

    11001200130014001500Total Time
    Acceptable Beam
    in Use
    0.000.000.000.170.570.73
    Beam Available
    but Not in Use
    0.000.380.240.410.011.03
    Beam Not Available
    or Unacceptable
    1.000.620.760.430.433.25
    Accelerator Con-
    figuration Change
    0.000.000.000.000.000.00
    Experiment
    Ready
    1.000.500.000.501.003.00
    Planned Config-
    uration Change
    0.000.000.000.000.000.00
    Unplanned
    Experiment Down
    0.000.501.000.500.002.00
    Hall not
    ready reasons
    Target0.000.000.000.000.000.00
    Data Acq0.000.000.000.000.000.00
    Other0.000.000.000.000.000.00
    HRSL0.000.000.000.000.000.00
    HRSR0.000.501.000.500.002.00
    HALL_OFF0.000.000.000.000.000.00

    Comments: Started shift with run 6411 and BHWP out. Run 6413 finishes slug 33. 1030 beam studies start. 1030 Ed Folts et al. go into the hall to do some maintaince on the right HRS flow meter. 1430 Start taking data again...

    Data Entry by: Higinbotham