Day Shift Summary
Started out the shift with 0.2 ua beam debugging MWDC
Many bad events with some TDCs shutting completely down.
10:00 AM Call MCC. Sweep Hall. Go to controlled access.
11:15 Brandon, Bob, and Richard trouble shooting front wire chamber looking for root cause of bad event 7.
See comments in Halog by Bob Michaels for details.
Polarized target group installing reference and 3He cell.
2:30 Nilanga and Bob troublw shooting MWDC
3:45 MWDC group discussing what steps to take next to eliminate oscillations and bad event 7.
3:55 PM Bogan decides to replace TDCs on Front chamber.
Shift Ends