keyword=swing shift summary
Still restricted access. Target work, BigBite work, moving the neutron detector back from 6 to 9 m. Collimators at the target removed. Nitrogen bottle installed.
There is evidence for a substantial misalignment of the beam line, in particular of the upstream one.
Survey of the beam line is planned for tomorrow.
Owl shift is canceled. Day shift probably partly canceled.