    Log entry time 22:14:48 on March 2,2006

    Entry number 164928

    keyword=swing shift summary

    Still restricted access. Target work, BigBite work, moving the neutron detector back from 6 to 9 m. Collimators at the target removed. Nitrogen bottle installed.

    There is evidence for a substantial misalignment of the beam line, in particular of the upstream one.

    Survey of the beam line is planned for tomorrow.
    Owl shift is canceled. Day shift probably partly canceled.