User name Sharon Beck
Log entry time 16:06:09 on March30,2006
Entry number 168939
keyword=Shift summary
8:30 - run 3504 stopped because one of the neutron arm bars tripped.
HV was restored, HV on bar (40,5) was shut down since it was too hot.
8:49-9:17 - run 3505. The run stopped for polarization meas. Target polarization: 53.5%
9:35 - run 3506. There were few drops in trigger 3 rates due to drops in the beam current. 10:03 - run stopped.
10:05 - HV on all Drift Chambers were raised.
10:10 - run 3507.
10:15 - stopped HAPPEX run 7162, ~0.45M events. Started run 7163.
11:12 - stopped run 3507.
HV on Drift Chambers were raised again by Brandon.
11:25-12:05 run 3508.
12:05 - Beam off by MCC for approx. 4 hours.
12:17 - start cosmic data run 3510. Thresholds were set to: (0):-50mV, (1):-10mV, (2):-25mV
12:24 - stopped HAPPEX run 7163. ~0.23M events.
Controlled access was requested for:
1) Putting the Berilium Oxide optic foil that had fallen off its place yesterday evening back in correct position.
2) Change units in Drift Chambers electronics.
12:30 - HallA is surveyed as a preperation to controlled access.
12:30 - Target polarization measurement: 51.7%
13:25 - Controlled access approved, except for the target region, which was not surveyed yet.
14:00 - Cosmic run was stopped due to jumper adjustments by Jack Segal.
14:30 - BeO optic foil position was fixed by replacing its holder (the old one melted).
~15:20 - Back to beam permit.
Checks performed with an empty target.
Raster spot looks fine (2x2 mm^2).
Thresholds were set back to their values for production mode (0):-320mV, (1):-25mV, (2):-145mV.
15:48 - Start production run