Started the shift with the reference cell in.
8:00 Run 4175. Reference cell, normal raster size.
8:30 Run 4176. Reference cell, 1.5x1.5 raster (4.5x3.15 in controls)
9:00 Beam off for pass change.
Requested controlled access.
10:00 NMR and EPR measurements were done.
12:00 Everyone out of hall
13:53 Beam back. Adjusted raster size. Asked MCC to work on Compton rates. Probably still needs a little tuning
14:21 Asked for beam off to put the target in and do an NMR.
14:30 Asked MCC to reinitialize Fast raster for the new energy. (3.290)
14:33 NMR done asked for 8uA.
15:05 Compton optimization is finished, asked MCC for proper beam position
15:13 start run 4189 , still optimizing, beam pos and raster
copntinue optimize raster size and scan beam position