    Log entry time 00:10:46 on July 21, 2006

    Entry number 174666

    keyword=Beam Time Accounting
    Hall A

    07/20/06 1600-2400
    Experiment #: CSR
    Shift Leader: AJ Sarty
    Shift Workers: Brandon Craver, Vina Punjabi

    16001700180019002000210022002300Total Time
    Acceptable Beam
    in Use
    0.000.000.000.000.000.000.000.000.00
    Beam Available
    but Not in Use
    0.000.000.000.000.000.000.000.000.00
    Beam Not Available
    or Unacceptable
    1.001.001.001.001.001.001.001.008.00
    Accelerator Con-
    figuration Change
    0.000.000.000.000.000.000.000.000.00
    Experiment
    Ready
    0.000.000.001.001.001.000.001.004.00
    Planned Config-
    uration Change
    0.000.000.000.000.000.000.000.000.00
    Unplanned
    Experiment Down
    1.001.001.000.000.000.001.000.004.00
    Hall not
    ready reasons
    Target1.001.001.000.000.000.001.000.004.00
    Data Acq0.000.000.000.000.000.000.000.000.00
    Other0.000.000.000.000.000.000.000.000.00
    HRSL0.000.000.000.000.000.000.000.000.00
    HRSR0.000.000.000.000.000.000.000.000.00
    HALL_OFF0.000.000.000.000.000.000.000.000.00

    Comments: 16:00-18:00 Target cooling in progress. 18:30 Hall locked up. 19:45 MCC starts to try bringing tuned beam in. 22:00-23:00 Access for quick target work. 23:00 Back up; MCC working on optics for incoming Hall A beamline.

    Data Entry by: AJ Sarty