    Log entry time 00:00:18 on August 3, 2006

    Entry number 177022

    keyword=Beam Time Accounting
    Hall A

    08/02/06 1600-2400
    Experiment #: LEDEX
    Shift Leader: E. Schulte
    Shift Workers: C. Perdrisat, P. Punjabi

    16001700180019002000210022002300Total Time
    Acceptable Beam
    in Use
    0.830.790.530.870.950.980.700.846.49
    Beam Available
    but Not in Use
    0.050.070.100.070.010.010.050.140.50
    Beam Not Available
    or Unacceptable
    0.130.150.370.050.050.020.240.021.03
    Accelerator Con-
    figuration Change
    0.000.000.000.000.000.000.000.000.00
    Experiment
    Ready
    1.001.001.001.001.001.001.000.887.88
    Planned Config-
    uration Change
    0.000.000.000.000.000.000.000.120.12
    Unplanned
    Experiment Down
    0.000.000.000.000.000.000.000.000.00
    Hall not
    ready reasons
    Target0.000.000.000.000.000.000.000.000.00
    Data Acq0.000.000.000.000.000.000.000.000.00
    Other0.000.000.000.000.000.000.000.000.00
    HRSL0.000.000.000.000.000.000.000.000.00
    HRSR0.000.000.000.000.000.000.000.000.00
    HALL_OFF0.000.000.000.000.000.000.000.000.00

    Comments: 16:00 Shift starts with taking of LD2 rad in data. 17:15 Re-zeroed beam position. 17:51 Stopped data taking because beam position unacceptable. 18:22 FFB back and we are taking data. 22:00 And All is Well... 23:23 Begin Moving Target to LH2 23:30 Requested beam back

    Data Entry by: E. Schulte