    Log entry time 08:07:31 on August 28, 2006

    Entry number 183407

    keyword=Beam Time Accounting
    Hall A

    08/28/06 0000-0800
    Experiment #: LEDEX
    Shift Leader: ron gilman
    Shift Workers: jonathan dumas, Lee Byungwuek

    00000100020003000400050006000700Total Time
    Acceptable Beam
    in Use
    0.540.000.000.170.920.610.800.773.82
    Beam Available
    but Not in Use
    0.070.000.000.540.050.340.130.071.19
    Beam Not Available
    or Unacceptable
    0.391.001.000.280.040.050.070.152.98
    Accelerator Con-
    figuration Change
    0.000.000.000.000.000.000.000.000.00
    Experiment
    Ready
    1.001.001.000.621.000.670.901.007.18
    Planned Config-
    uration Change
    0.000.000.000.000.000.330.100.000.43
    Unplanned
    Experiment Down
    0.000.000.000.380.000.000.000.000.38
    Hall not
    ready reasons
    Target0.000.000.000.000.000.000.000.000.00
    Data Acq0.000.000.000.380.000.000.000.000.38
    Other0.000.000.000.000.000.000.000.000.00
    HRSL0.000.000.000.000.000.000.000.000.00
    HRSR0.000.000.000.000.000.000.000.000.00
    HALL_OFF0.000.000.000.000.000.000.000.000.00

    Comments: MPS BCM issue around 1-2 AM. Capture issues afterward until ~3:30. DAQ problems until 4:00. Then taking data.

    Data Entry by: ron gilman