Shift Summary
------------------------------------
8:19 MCC called and want to fix the beam trips. It might take 30mins
8:53 beam is back
10:10 Q1 on both left and right arm tripped and also dipole on left arm tripped due to the low He flow. Went to controlled access and reset the quads.
11:10 Quads reset locally and D1 on left arm was also reset. ready to take the beam
12:41 Q1s tripped again. had to go to controlled access to fix them.
13:27 beam is back and resumed e-p calibration runs
Run Summary(e-p elastic)
-------------------------------------
Run Events
5377 3.9M
5378 5.0M
5379 2.4M
5380 2.9M
5381 5.0M
5382 5.0M
5383 1.3M