    Log entry time 00:03:04 on October 4,2006

    Entry number 186248

    keyword=shift summary - swing shift

    MCC started restoring beam around 7:00.

    Sirish checked the compton background rates around 10:00, and it looked OK.

    MCC took beam to start delivery to Hall B - restored beam to Hall A at about 10:30. We did a raster size scan and determined that requesting a 12mm x 12mm raster gave us a 1.5mm x 2mm raster.

    23:30 - Started pointing runs.

    1034 - pointing run with no sieve slits (carbon target)

    1035 - run with sieve slit in left arm (carbon target)

    Shift ends during sieve slit run.