0800 | 0900 | 1000 | 1100 | 1200 | 1300 | 1400 | 1500 | Total Time | |
---|---|---|---|---|---|---|---|---|---|
Acceptable Beam in Use | 0.79 | 0.20 | 0.00 | 0.00 | 0.00 | 0.00 | 0.82 | 0.98 | 2.78 |
Beam Available but Not in Use | 0.13 | 0.74 | 0.97 | 0.98 | 0.98 | 0.99 | 0.10 | 0.01 | 4.91 |
Beam Not Available or Unacceptable | 0.08 | 0.06 | 0.03 | 0.02 | 0.02 | 0.01 | 0.08 | 0.02 | 0.32 |
Accelerator Con- figuration Change | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
Experiment Ready | 1.00 | 0.25 | 0.00 | 0.00 | 0.00 | 0.00 | 1.00 | 1.00 | 3.25 |
Planned Config- uration Change | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
Unplanned Experiment Down | 0.00 | 0.75 | 1.00 | 1.00 | 1.00 | 1.00 | 0.00 | 0.00 | 4.75 |
Hall not ready reasons | |||||||||
Target | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
Data Acq | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
Other | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
HRSL | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
HRSR | 0.00 | 0.75 | 1.00 | 1.00 | 1.00 | 1.00 | 0.00 | 0.00 | 4.75 |
HALL_OFF | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
Comments: Probelms with the right dipole for most of the shift. From 2 pm on we take data in kinematics A5.
Data Entry by: Higinbotham