    User name M Jones

    Log entry time 07:55:38 on October 6,2006

    Entry number 186450

    keyword=Owl shift summary

    Start of shift with hall in restricted access as Mark Stevens was
    working to fix problem with right arm dipole communications.
    Mark finished work at aorund 1:45 and the dipole was cycling back
    to the momentum of 1.5607

    At 3:21 the right dipole had reached the desired setting and we started a run 1095 for A2 setting.

    While doing the shift checklist at around 3:30 noticed that the
    argon pressure was at 10psi. See elog 186437 for details, but
    the upshot is that the argon is back at 2400 and the argon had probably just gone off.

    Finish 1095 with 5M which finishes A2 setting.

    Change to A1 setting. Only able to get to 62uA while
    keeping ESr hall A flow to about 11.3
    Start run 1096 and take 5M which all that is needed for A1 setting.

    Change to A9 setting . Need to cycle left arm Q2 and Q3 while
    setting to 1.0701 . Start run 1097.

    In start of run menu for run type find typo as made two +6%
    and no +8%. Force to select +6% but add comment. Modify the
    runstart.tcl to fix typo.

    Finish 1097 with 3.8M
    Start 1098 ( in middle of run notice that AY = BY = +1mm
    ask MCC to zero it) finish with 2.4

    Change to kinematic setting A8
    Start run 1099 at 52uA giving DT=30%