User name jpchen
Log entry time 16:07:50 on October 9,2006
Entry number 186661
keyword=Day shift summary
Day shift summary
Shift workers: J. P. Chen, J. Glister.
8:00 controlled access for configuration change - switching from LH2 to helium target.
9:00 ESR 4K coolant flow went to zero. Cryo is doing switching
of the cryotarget cooling from ESR to CHL. Magnets level dropping, all magnets ramping down.
Mark Stevens working on the right HRS magnet control.
11:00 ESR 4K flow back.
12:50 Set the left spectrometer.
16:00 still waiting for helium target to be rady adn right spectrometer work.