• Main INDEX
  • Monthly INDEX
  • PREV
  • NEXT

    User name Jack

    Log entry time 19:43:55 on October13,2006

    Entry number 187010

    keyword=Magnet work today

    Mark, Scot, Heidi and I went in the hall to work on the magnet communications. Mark replaced the Field Regulation module on the NMR meter. That module has the GPIB interface to the EPICS VME crate. We found the octagon computer for the Right Dipole in a bad state. The program to interface to the supply was not running. We ramped the dipole down so we could cycle power on the octagon. We also cleaned up the wiring for the serial connections for both dipoles. Lots of messing around with the magnet settings and serial cables, but eventually things seemed to be up and running.