Main INDEX
Monthly INDEX
PREV
NEXT
User name eschulte
Log entry time 17:03:13 on October14,2006
Entry number 187115
keyword=HRS-L NMR Probe A Down
Lost HRS-L NMR (Probe A). Rebooted according to the How-To page.
Just rebooting the NMR was unsuccessful. We took a look at the iocha14 left magnet screens (power supply screens) and found that they were all not communicating. We tried to reboot iocha14.
After the APC screen reported that the reboot was complete, the communciation was still not restored. Tried one more time to reboot from the APC screens. This raised a communication alarm and the general tools and, finally, the communications came back to life!
The momentum set point was reset and the NMR was switched back on. Data taking was restarted with Run #1327. Run #1326 was stopped when we started working on the magnets. The data appears to be OK for Run #1326, so the problem was most likely communication only.
Also noticed a high-cryo for Q2 after communication was restored.
FIGURE 1
FIGURE 2