Main INDEX
Monthly INDEX
PREV
NEXT
User name eschulte
Log entry time 01:00:33 on October 17, 2006
Entry number 187357
keyword=Run Coordinator Summary 10/15 Day Shift through 10/16 Swing Shift
10/15 Day shift started with further carbon single foil running with the
A10 kinematics. Data taking went smoothly through the end of Swing shift
on 10/15. A loss of communication with ioch14 (HRS-L magnets) led to
some confusion when the ioc appeared to reboot properly, but the Hall A
Tools MEDM screen did not update to reflect this. The tech on-call was
consulted. He came in when we though we might need an access to
re-establish communications. The access was avoided when he recognized
the problem he had seen before, and quit and restarted the Hall A Tools.
This resolved the non-updating screen problem. Data taking on carbon
continued until just 07:00 10/16.
At approximately 06:55 on 10/16, the ARM came to the hall to put Hall A
into restricted access for the change over to Q^2=1.3 GeV/c. The survey
went well, with Ed Folts turning of the Compton polarimeter laser, which
was powered up at the time of the sweep. The ARM was unwilling to survey
the transfer line until the laser was turned off. A bit after 07:00 Dave
Meekins came over to do the target change back to hydrogen. This went
well and without incident. The target change-over was completed by
09:30. By 08:00 the hall was busy with surveyers and technicians. Both
HRS were surveyed in place, moved, and resurveyed. The survey was
completed by 15:30. Several smaller maintenance activities, including
work on serial cables causing communications problems commenced. The
Compton polarimeter group worked on the polarimeter during the access.
Shortly before 10:00 the CHL 4K helium flow was shut of to the hall. An
investigation of the incident revealed a communication problem between
target and cryo groups. The problem was resolved and coolant flow was
restored. The target partially warmed up, and J.P. restored it to
operating conditions. A caution: One must be very careful adjusting the
JT valves with the 4K flow, as the response is even more sensitive than
usual. Without care, we can wind up tripping closed the feed valve
supplying coolant to the hall, thus warming up the target. Very bad.
Shortly after 15:30 Ed Folts reported that work in the hall was completed
and I called MCC to have the hall returned to Beam Permit status. The
sweep of the hall started around 16:30 and was completed by about 16:50.
MCC reported that they would be sending tuning beam by 17:15. After the
re-establishment of beam to the hall, the Compton group did some work
with the Compton polarimeter. They had some difficulties, and gave the
beam back to the shift crew, who completed the requested harp scans,
re-established the 2mmX2mm raster, and prepared to start taking pointing
data.
The day ended with pointing data (seive slit) with the single foil carbon
target. The going is slow. It will take several hours to complete all
of the pointing measurements.
It was a good day!