    Log entry time 00:00:40 on October 26, 2006

    Entry number 188299

    keyword=Beam Time Accounting
    Hall A

    10/25/06 1600-2400
    Experiment #: e03104
    Shift Leader: E. Schulte
    Shift Workers: B. Briscoe

    16001700180019002000210022002300Total Time
    Acceptable Beam
    in Use
    0.640.840.970.960.970.680.940.936.93
    Beam Available
    but Not in Use
    0.330.140.000.020.000.050.020.040.60
    Beam Not Available
    or Unacceptable
    0.040.020.030.020.030.270.040.030.47
    Accelerator Con-
    figuration Change
    0.000.000.000.000.000.000.000.000.00
    Experiment
    Ready
    0.670.831.001.001.000.951.000.957.40
    Planned Config-
    uration Change
    0.000.070.000.000.000.000.000.000.07
    Unplanned
    Experiment Down
    0.330.080.000.000.000.050.000.050.52
    Hall not
    ready reasons
    Target0.000.000.000.000.000.000.000.000.00
    Data Acq0.000.000.000.000.000.000.000.000.00
    Other0.000.000.000.000.000.000.000.000.00
    HRSL0.330.080.000.000.000.050.000.050.52
    HRSR0.000.000.000.000.000.000.000.000.00
    HALL_OFF0.000.000.000.000.000.000.000.000.00

    Comments: 16:00 Working on resetting HRS-L Dipole 17:05 HRS-L Dipole reset 17:24 Finished closing FPP Doors 21:18 Start PZT 21:34 MCC called to let us know the're sending beam back at 60uA.

    Data Entry by: E. Schulte