16:00 Shift began with
Photocathode work to increase the beam current still in progress
Hall is under controlled access
18:15 MCC called. MCC is ready to deliver the beam to the hall.
Alexandre working in the hall has been called and he will leave the
hall.
18:20 Changing to kinematics #6
19:56 MCC is going to put tune beam into the hall.
21:55 Finally beam is back to the hall
22:05 Run 1391 started.
24:00 Run in progress, but beam is quite unstable beyond 50uA.