    16:00 Shift began with
          Photocathode work to increase the beam current still in progress
          Hall is under controlled access
    18:15 MCC called. MCC is ready to deliver the beam to the hall.
          Alexandre working in the hall has been called and he will leave the 
          hall.
    18:20 Changing to kinematics #6
    19:56 MCC is going to put tune beam into the hall.
    21:55 Finally beam is back to the hall
    22:05 Run 1391 started.
    24:00 Run in progress, but beam is quite unstable beyond 50uA.