    keyword=Beam Time Accounting
    Hall A

    02/12/07 0000-0800
    Experiment #: E05-004
    Shift Leader: E. Schulte
    Shift Workers: J. Miller

    00000100020003000400050006000700Total Time
    Acceptable Beam
    in Use
    0.960.750.770.970.920.980.340.656.33
    Beam Available
    but Not in Use
    0.040.230.220.030.070.020.070.210.88
    Beam Not Available
    or Unacceptable
    0.010.020.010.000.000.000.580.150.77
    Accelerator Con-
    figuration Change
    0.000.000.000.000.000.000.000.000.00
    Experiment
    Ready
    1.000.880.831.000.951.001.001.007.67
    Planned Config-
    uration Change
    0.000.120.170.000.050.000.000.000.33
    Unplanned
    Experiment Down
    0.000.000.000.000.000.000.000.000.00
    Hall not
    ready reasons
    Target0.000.000.000.000.000.000.000.000.00
    Data Acq0.000.000.000.000.000.000.000.000.00
    Other0.000.000.000.000.000.000.000.000.00
    HRSL0.000.000.000.000.000.000.000.000.00
    HRSR0.000.000.000.000.000.000.000.000.00
    HALL_OFF0.000.000.000.000.000.000.000.000.00

    Comments: 00:00 Started shift on B4C target & requested a current adjustment down to 3uA from 5uA. 01:08 Request change of target ot Li. 01:15 Request 3uA back from MCC 02:28 Request target change back to Ta. Setup spectrometer for next kinematic setting 02:37 Request 15uA beam on Ta target in new kinematics setting. Restart production running. 04:41 Request change of target to C 04:43 Request 10uA from MCC 07:00 Lost beam 07:14 Beam looks stable-ish so we re-started DAQ. 07:56 Request change to B4C target.

    Data Entry by: E. Schulte