Shift goal was to put 1.9 C on Pb3 at kinematics 10.
Restored beam shape and raster parameters to have beam
wider in vertical be keeping area the same (see separate
entry). Beam now is 4x5mm^2 (raster 7.3/6.4)
Put Pb3 target in, after checking with C target
1789-1792 Runs are C test runs with different raster
parameters.
Following table is run#, start time, current, charge, cum/tive charge
Started with ~3.5x10-5 beam spread, spread grew to 4.5x10-5
when current increased to 40uA
1793, 17:00, 10uA, 0.007 C, 0.061 C (cum Q)
1794, 17:12, 20uA, 0.016 C, 0.077
1795, 17:26, 30uA, 0.019 C, 0.096
1796, 17:38, 40uA, 0.015 C, 0.110 (for I=40uA: DE/E=4.5x10-5)
1797, 17:48, 30uA, 0.012 C, 0.122
1798, 17:56, 40uA, 0.032 C, 0.154 (from here on DE/E < or = 4.5x10-5)
1799, 18:11, 40uA, 0.032 C, 0.186
1800, 18:26, 40uA, 0.020 C, 0.206
1801, 18:39, 40uA, 0.032 C, 0.238
Prescale factor change to make runs longer (per Konrad's suggestion)
1802, 18:54, 40uA, 0.060 C, 0.298
1803, 19:22, 40uA, 0.060 C, 0.358
1804, 19:49, 40uA, 0.060 C, 0.418
1805, 20:19, 40uA, 0.060 C, 0.478
1806, 20:47, 40uA, 0.060 C, 0.538
1807, 21:18, 40uA, 0.060 C, 0.598
1808, 21:47, 40uA, 0.060 C, 0.658
1809, 22:16, 40uA, 0.035 C, 0.693 TOTAL CHARGE on Pb so far kin 10
Beam off for ~15mins (estimate) to power cycle machine racks.
MCC update: looks like an hour not 15 mins!
No beam till end of shift, put target in EMPTY position