• Main INDEX
  • Monthly INDEX
  • PREV
  • NEXT

    User name adaq

    Log entry time 00:00:40 on April 19, 2007

    Entry number 199515

    keyword=Beam Time Accounting
    Hall A

    04/18/07 1600-2400
    Experiment #: E04-018
    Shift Leader: P. Solvignon
    Shift Workers: K. Allada

    16001700180019002000210022002300Total Time
    Acceptable Beam
    in Use
    0.000.000.000.000.000.000.000.000.00
    Beam Available
    but Not in Use
    0.000.000.000.000.000.000.000.000.00
    Beam Not Available
    or Unacceptable
    0.100.070.060.070.060.040.050.100.55
    Accelerator Con-
    figuration Change
    0.900.930.940.930.940.960.950.907.44
    Experiment
    Ready
    1.001.001.001.001.001.001.001.008.00
    Planned Config-
    uration Change
    0.000.000.000.000.000.000.000.000.00
    Unplanned
    Experiment Down
    0.000.000.000.000.000.000.000.000.00
    Hall not
    ready reasons
    Target0.000.000.000.000.000.000.000.000.00
    Data Acq0.000.000.000.000.000.000.000.000.00
    Other0.000.000.000.000.000.000.000.000.00
    HRSL0.000.000.000.000.000.000.000.000.00
    HRSR0.000.000.000.000.000.000.000.000.00
    HALL_OFF0.000.000.000.000.000.000.000.000.00

    Comments:

    Data Entry by: P. Solvignon