• Main INDEX
  • Monthly INDEX
  • PREV
  • NEXT

    User name adaq

    Log entry time 00:01:22 on May 15, 2007

    Entry number 202073

    keyword=Beam Time Accounting
    Hall A

    05/14/07 1600-2400
    Experiment #: E04-018
    Shift Leader: A. Kelleher
    Shift Workers: K. Allada

    16001700180019002000210022002300Total Time
    Acceptable Beam
    in Use
    0.000.000.000.000.000.000.000.000.00
    Beam Available
    but Not in Use
    0.000.000.000.000.000.000.000.000.00
    Beam Not Available
    or Unacceptable
    0.100.010.050.000.000.050.060.000.29
    Accelerator Con-
    figuration Change
    0.900.990.951.001.000.950.941.007.71
    Experiment
    Ready
    1.001.001.001.001.001.001.001.008.00
    Planned Config-
    uration Change
    0.000.000.000.000.000.000.000.000.00
    Unplanned
    Experiment Down
    0.000.000.000.000.000.000.000.000.00
    Hall not
    ready reasons
    Target0.000.000.000.000.000.000.000.000.00
    Data Acq0.000.000.000.000.000.000.000.000.00
    Other0.000.000.000.000.000.000.000.000.00
    HRSL0.000.000.000.000.000.000.000.000.00
    HRSR0.000.000.000.000.000.000.000.000.00
    HALL_OFF0.000.000.000.000.000.000.000.000.00

    Comments:

    Data Entry by: A. Kelleher