    8:00 AM Day Shift
    SL R. Lindgren
    TO R. Gilman
    No Beam RF Problem
    9:55 AM Hall A access by MCC to change out an FSD card
    11:00 AM Beam Loss Monitor is still being repaired in Hall A.
    Another FSD card is being tried. The HARP wire was repaired.
    11:40 AM Beam Back
    Start Run 4095 Stop Run 12:06 Beam Off
    MCC reports Injector Voltage Gradient incorrect? Beam off.
    12:30 Beam Back

    BoB Michaels Rebooted Coda. Don't remember the time.

    10:03 Start Run 4093 Stop 10:42 Cosmics
    11:20 Start Run 4094 Stop 11:25 Cosmics

    11:40 Start Run 4095 Stop 12:05 0.27M
    !2:54 Start Run 4096 Stop 13:13 Junk
    12:35 Start Run 4097 Stop 14:18 1.25M
    14:19 Start Run 4098 Stop 15:05 1.25M
    15:06 Start Run 4099 Stop 15:53 1.25M
    15:54 Start Run 4100 Stop

    16:00 PM Day Shift Ends