Owl Shift Summary
00:00 Radiator is in (position 5), running 3He (loop1), 30 uA,
run number 1405
01:15 After discussion with Hall C and Xiaodong we decided to
continue running with radiator in at 30 uA for about 1.5
more hours (see entry 206111)
01:45 Beam current (downstream cavity) started to drop in our
stripchart reaching slowly 26 uA,
then moved back slowly toward 30 uA (see entry 206112)
04:05 Radiator OUT, beam current at 50 uA, run 1411 started
05:50 Radiator IN, beam current at 30 uA, run 1413 started
NOTE:
To maximize efficiency and avoid Hall A / C beam current delivery problems we coordinated with Hall C: we asked for 50 uA beam when Hall C ran at 40 uA.
We got the planned 1:4 statistics ratio for IN:OUT radiator events.
Down stream BCM has significantly drifted respect to Up stream one, 3 times during the shift (see entry 206112 and follows up).