User name V. Sulkosky
Log entry time 08:09:56 on July 3,2007
Entry number 207341
keyword=Owl Shift Summary
Owl Shift Summary
-------------------------------------------------------------------------------
Shift Crew:
Vincent Sulkosky (SL/TO)
Gordon Lott (3rd)
Major Events:
-------------------------------------------------------------------------------
00:00 Begin shift with kinematic # 3, 3He, radiator IN 45 uA.
01:40 Left HV tripped.
02:03 Cleared FPP HV problem.
03:29 Attempt to reset FPP HV again.
05:27 Move radiator OUT.
05:30 Ask MCC for 50 uA.
06:13 Ask for 45 uA of beam.
06:15 Move Radiator IN.
Run Summary
-------------------------------------------------------------------------------
Run # Begin End Comments
1712 23:54 00:50 3He target, 45 uA beam, Radiator IN, 1.00 M events.
1713 00:50 01:42 3He target, 45 uA beam, Radiator IN, 0.90 M events.
1714 02:03 03:02 3He target, 45 uA beam, Radiator IN, 1.00 M events.
1715 03:03 03:28 3He target, 45 uA beam, Radiator IN, 0.45 M events.
1716 03:37 04:32 3He target, 45 uA beam, Radiator IN, 1.00 M events.
1717 04:33 05:26 3He target, 45 uA beam, Radiator IN, 1.00 M events.
1718 05:31 ----- junk, need to change PS factors.
1719 05:33 06:12 3He target, 50 uA beam, Radiator OUT, 0.62 M events
1720 06:15 07:11 3He target, 45 uA beam, Radiator IN, 1.00 M events.
1721 07:11 ----- 3He target, 45 uA beam, Radiator IN, passed to Day shift.