    Log entry time 23:57:18 on July 8, 2007

    Entry number 208146

    keyword=Beam Time Accounting
    Hall A

    07/08/07 1600-2400
    Experiment #: E04-018
    Shift Leader: A. Camsonne
    Shift Workers: S. Marrone

    16001700180019002000210022002300Total Time
    Acceptable Beam
    in Use
    0.620.900.850.920.920.920.920.936.97
    Beam Available
    but Not in Use
    0.050.050.050.050.050.050.050.050.40
    Beam Not Available
    or Unacceptable
    0.330.050.100.030.030.030.030.020.63
    Accelerator Con-
    figuration Change
    0.000.000.000.000.000.000.000.000.00
    Experiment
    Ready
    1.001.001.001.001.001.001.001.008.00
    Planned Config-
    uration Change
    0.000.000.000.000.000.000.000.000.00
    Unplanned
    Experiment Down
    0.000.000.000.000.000.000.000.000.00
    Hall not
    ready reasons
    Target0.000.000.000.000.000.000.000.000.00
    Data Acq0.000.000.000.000.000.000.000.000.00
    Other0.000.000.000.000.000.000.000.000.00
    HRSL0.000.000.000.000.000.000.000.000.00
    HRSR0.000.000.000.000.000.000.000.000.00
    HALL_OFF0.000.000.000.000.000.000.000.000.00

    Comments:

    Data Entry by: A. Camsonne