User name Yi Qiang
Log entry time 16:02:05 on January30,2008
Entry number 228064
keyword=Day Shift Summary
Shift Workers
----------------------------------------------------------
SL: Yi Qiang
TO: Mitra Shabestari
Shift Summary
----------------------------------------------------------
08:00 Shift began with 80 uA on Carbon target
08:45 Begin pass change from 3 to 1.
09:00-13:45 Access for reparing NIM crate and modifing DAQ
13:45 Beam tuning started
14:00 Move Right HRS to 19 degrees and set both
momenta to 0.948 GeV/c
14:50 CW beam in hall
15:21 Harp Scan
16:00 Still waiting for beam tuning done
Run Summary
----------------------------------------------------------
Run# From to I(uA) Event# Target Comments
3645 07:16 08:45 80uA 290k C Raster ON