    Log entry time 07:44:01 on February 1,2008

    Entry number 228536

    keyword=Target warming-up. Turned of HP heater and fan

    Completed the 15K warm-up procedure with MCC: Closed J-T valve, switched to warm return.
    Went into the hall, turned off Hp heater and Fan. Unplug the fan controller.
    Loop3 is at 30-60K, out of liquid. Will leave it slowly warming up.
    Vacuum is at 5x10-5.
    Moved to EMPTY position to allow MCC to send beam to Hall A for their beam study.