    Log entry time 08:17:07 on April 4, 2008

    Entry number 229856

    keyword=Beam Time Accounting
    Hall A

    04/04/08 0000-0800
    Experiment #: E04-007
    Shift Leader: dhamilton
    Shift Workers: Nelyubin

    00000100020003000400050006000700Total Time
    Acceptable Beam
    in Use
    0.600.060.000.000.000.220.000.141.01
    Beam Available
    but Not in Use
    0.330.000.000.000.120.000.000.000.44
    Beam Not Available
    or Unacceptable
    0.080.941.001.000.880.781.000.876.56
    Accelerator Con-
    figuration Change
    0.000.000.000.000.000.000.000.000.00
    Experiment
    Ready
    0.671.001.001.000.881.001.001.007.55
    Planned Config-
    uration Change
    0.330.000.000.000.000.000.000.000.33
    Unplanned
    Experiment Down
    0.000.000.000.000.120.000.000.000.12
    Hall not
    ready reasons
    Target0.000.000.000.000.000.000.000.000.00
    Data Acq0.000.000.000.000.000.000.000.000.00
    Other0.000.000.000.000.000.000.000.000.00
    HRSL0.000.000.000.000.000.000.000.000.00
    HRSR0.000.000.000.000.000.000.000.000.00
    HALL_OFF0.000.000.000.000.000.000.000.000.00
    Bbite0.000.000.000.000.120.000.000.000.12

    Comments: Problems between 5 am and 8 am due to unstable beam alignment.

    Data Entry by: dhamilton