If Eugene is still around and willing, finish up the Moller measurement.
-
Insert the BeO target, make sure it is visible on the target camera
and the spot matches the marker spot on the screen.
-
Have MCC perform a HARP scan. Post the result (the x and y widths) in
the HALOG. These should be ~100µm. +/- 30µm. is OK. +/-
100µm is right out.
-
Move to Empty target position. Turn on the HV to the Bigbite trigger
planes (S0 through S7) and the Bigbite MWDC (S14).
-
Check the T1 and T2 rates (on BigBite Scaler screen) to establish a
baseline. HALOG them.
-
Move to Holey Carbon target. Check T1 and T2 rates and compare to
rates obtained from empty target. They should be comparable. If
not... need to find the Hole in the target. See below.
-
Continue production running. LHRS angle = 16.5°,
p0=0.986GeV/c. 1M events/run. Set all prescales to have
T1, T2, T3, T4, T7, T8 at 10Hz.. prescales for T5 and T6 set to 1.
|