Day shift summary:
shift workers: J. P. Chen (SL), D. Armstrong (TO), X. Qian (3rd).
8:00 production at Kin. L: LHRS at 12.451 degree, 1.007 GeV/c
BigBite 105 degree, 390 A,
At the beginning of shift, 0.144 C.
11:00 RF problem. beam off. (run 4260).
11:20 Beam back.
12:55 Nikos started to turn on FPP HVs for FPP test.
13:15 FPP HVs all set to 1750 V. Started FPP test (run 4273-4282).
FPP HV settings: 1750, 1800, 1850, 1875, 1700, 1775, 1825, 1900V.
14:17, MCC called that beam off to change Wien angle for Hall C
(run 4279).
14:30 beam back, Wien angles changed from -40 to -30 degree.
14:53-14:56 Wien cangle change to -50 degree.
14:56 turned off FPP HVs.
15:20 MCC cchange Wien angle to -40 degree.
Moller starts after the Wien angle change.
run 4241/4242/4243/4244/4245/4246/4247/4248/4249/4250/4251
4252/4253/4254/4255/4256/42574258/4259, good runs, 1M.
run 4260 RF problem. 0.94M.
run 4261/4262/4263/4264/4265/4266/4267/4268/4269/4270/4271/4272. 1M.
Following runs also for FPP test, 1M events each run:
run#, FPP HV
4273, 1750
4274, 1800
4275, 1850
4276, 1875
4277, 1700
4278, 1775
4279, 1825, 252K, stopped for wien angle change from -40 degree to -30 degree (next run will be -30 degree).
4280, 1825, wien angle -30 degree.
4281, 1900.
4282, 1900. 514K. stopped for another Wien angle change.
FPP test ends.
4283/4284, Wien angle -50 degree. 1M.
4285. Wien -50 degree, 435K, stopped to change Wien angel back to -40 degree.