    Log entry time 16:01:51 on May 20, 2008

    Entry number 238969

    keyword=Beam Time Accounting
    Hall A

    05/20/08 0800-1600
    Experiment #: E08-007
    Shift Leader: A. Sarty
    Shift Workers: Huan Yao (TO), A. Saha

    08000900100011001200130014001500Total Time
    Acceptable Beam
    in Use
    0.000.000.000.000.000.000.000.000.00
    Beam Available
    but Not in Use
    0.000.000.000.000.000.000.000.000.00
    Beam Not Available
    or Unacceptable
    1.001.001.001.001.001.001.001.008.00
    Accelerator Con-
    figuration Change
    0.000.000.000.000.000.000.000.000.00
    Experiment
    Ready
    1.001.001.001.001.001.000.501.007.50
    Planned Config-
    uration Change
    0.000.000.000.000.000.000.000.000.00
    Unplanned
    Experiment Down
    0.000.000.000.000.000.000.500.000.50
    Hall not
    ready reasons
    Target0.000.000.000.000.000.000.000.000.00
    Data Acq0.000.000.000.000.000.000.000.000.00
    Other0.000.000.000.000.000.000.000.000.00
    HRSL0.000.000.000.000.000.000.500.000.50
    HRSR0.000.000.000.000.000.000.000.000.00
    HALL_OFF0.000.000.000.000.000.000.000.000.00
    Bbite0.000.000.000.000.000.000.000.000.00

    Comments: No beam all shift. 08:00-09:00 still re-establishing orbit lock...almost ready to deliver beam when machine taken down by passing storm/lightning. Recovery from this event still ongoing at shift's end.

    Data Entry by: sarty