5/29/08 Swing shift
John LeRose (SL)
Jin Huang (TO)
Werner Boeglin (3rd)
Left Arm 0.8526 GeV, 47 deg.
BigBite 45 deg. 700 Amps
At start of shift HAPPEX beam studies underway.
16:30 MCC says the beam is ours
16:23 1702 Test Production 6cm LH2
16:38 1703 Test Production 6cm LH2
Prescales etc. adjusted ready for full production running
16:45 1704 Production 6cm LH2 K7-D-2
17:27 1705 Production 6cm LH2 K7-D-2 probably garbage
17:41 ROC 10 failed. We reset it.
17:48 1706 Production 6cm LH2 K7-D-2
18:53 MCC has box supply problem estimate 20 minutes to recover
It takes a lot longer than 20 minutes.
22:15 Brad makes an access to adjest the BigBite Cerenkov gas
flow see halog 240346
22:42 1707 pedestal run (no beam)
At shift end still no beam