• Main INDEX
  • Monthly INDEX
  • PREV
  • NEXT
    Make New Entry, Make Followup Entry

    User name adaq

    Log entry time 16:00:23 on November 5, 2008

    Entry number 246928

    keyword=Beam Time Accounting
    Hall A

    11/05/08 0800-1600
    Experiment #: E06-010
    Shift Leader: E. Schulte
    Shift Workers: Y. Zhihong, D. Gaskell

    08000900100011001200130014001500Total Time
    Acceptable Beam
    in Use
    0.690.760.000.000.000.470.630.873.42
    Beam Available
    but Not in Use
    0.030.040.780.210.000.120.170.031.37
    Beam Not Available
    or Unacceptable
    0.280.200.220.791.000.420.220.103.23
    Accelerator Con-
    figuration Change
    0.000.000.000.000.000.000.000.000.00
    Experiment
    Ready
    1.001.000.000.000.501.000.831.005.33
    Planned Config-
    uration Change
    0.000.001.001.000.500.000.000.002.50
    Unplanned
    Experiment Down
    0.000.000.000.000.000.000.170.000.17
    Hall not
    ready reasons
    Target0.000.000.000.000.000.000.000.000.00
    Data Acq0.000.000.000.000.000.000.170.000.17
    Other0.000.000.000.000.000.000.000.000.00
    HRSL0.000.000.000.000.000.000.000.000.00
    HRSR0.000.000.000.000.000.000.000.000.00
    HALL_OFF0.000.000.000.000.000.000.000.000.00
    Bbite0.000.000.000.000.000.000.000.000.00

    Comments: 08:00 Taking data on H2 10:00 MCC has an IOC issue, so we called for our controlled access. 11:49 RC reports that MCC is still fiting an IOC problem. 12:35 MCC ready to send RF to hall. Request hall back to Beam Permit. 13:00 Requested target change to "Optics" 13:23 Request a harp scan from MCC 13:39 Request 4x4 raster at 5uA. 14:33 begin 2 hours of reference cell, hydrogen data. 14:38 DAQ failure, rebooted ROCs 14:47 DAQ restart.

    Data Entry by: E. Schulte