Log entry time 20:32:14 on November 19, 2008
Entry number 249793
keyword=Experiment: summary for 11/18(day)-11/19(day)
The experiment is taking data for NegNeg polarity, vertical target
polarization.
The target polarization is more than 60%, the beam current is 12uA.
The data look OK.
Beam time accounting in hours:
date ABU BANU BNA losses
2008/11/18 day 2.32 3.59 2.08 unclear
2008/11/18 swing 0.00 6.00 2.00 control access 6h - Q2R(short), fire
alarm (long)
2008/11/19 owl 6.62 0.42 0.95 smooth running
2008/11/19 day 4.05 0.99 2.94 Q1 issues
Technical problems:
11/18 16:00 - a compressor for the dump dehumidifier started smoking.
Dave Kausch turned it off. It has to be repaired soon.
11/18 18:00 - a problem with the Q2R helium meter was fixed.
11/19 day - Q1 trips more and more frequently
Status of commissioning of other equipment:
Gas Cherenkov: the high background in the PMTs is being investigated
RICH: DAQ problems
Compton electron detector: DAQ problems