    User name adaq

    Log entry time 00:03:50 on November 29, 2008

    Entry number 251253

    Followups:

    keyword=Beam Time Accounting
    Hall A

    11/28/08 1600-2400
    Experiment #: E06-010
    Shift Leader: Gao
    Shift Workers: M. Shabestera, S. Sirca

    16001700180019002000210022002300Total Time
    Acceptable Beam
    in Use
    0.570.310.300.180.570.240.550.323.03
    Beam Available
    but Not in Use
    0.230.330.340.340.330.490.330.663.04
    Beam Not Available
    or Unacceptable
    0.200.370.360.480.110.270.130.021.94
    Accelerator Con-
    figuration Change
    0.000.000.000.000.000.000.000.000.00
    Experiment
    Ready
    1.001.001.001.001.001.001.000.837.83
    Planned Config-
    uration Change
    0.000.000.000.000.000.000.000.170.17
    Unplanned
    Experiment Down
    0.000.000.000.000.000.000.000.000.00
    Hall not
    ready reasons
    Target0.000.000.000.000.000.000.000.000.00
    Data Acq0.000.000.000.000.000.000.000.000.00
    Other0.000.000.000.000.000.000.000.000.00
    HRSL0.000.000.000.000.000.000.000.000.00
    HRSR0.000.000.000.000.000.000.000.000.00
    HALL_OFF0.000.000.000.000.000.000.000.000.00
    Bbite0.000.000.000.000.000.000.000.000.00

    Comments: Most of the shift was spent on reference cell data taking: 3He, N2, empty and H2. Started polarized 3He production run towards the end of the shift.

    Data Entry by: Gao