User name Yi Qiang
Log entry time 11:18:03 on November 29, 2008
Entry number 251302
keyword=Experiment Summary for Nov 28, Owl - Swing
Summary for Nov 28 (owl - swing)
Smooth data taking.
Beam in Use
shift |
ABU |
BANU |
BNA |
2008/11/28 owl | 6.00 |
0.67 | 1.33 |
2008/11/28 day | 0.69 |
3.22 | 4.08 |
2008/11/28 swing | 5.50 |
0.56 | 1.94 |
total | 12.19 |
4.45 | 7.35 |
Main events/issues:
- 10:30 - 12:30: Rotate Target Polarization from Vertical + to
Transverse -
- 12:30 - 15:00: Moller Tuning and Measurement: 80.5% beam polarization
- 15:00 - 15:30: Target EPR Calibration for Transverse Pumping
- 15:30 - 23:15: Reference Cell Measurement (1h 3He, 10m Emp, 1h
N2, 3h H2)
- other time: Production
Plans for the next few days: