    User name .Shabestari

    Log entry time 00:05:33 on December 3,2008

    Entry number 251788

    keyword=Swing shift summary

    Swing shift summary December 2, 2008

    SL : Mitra Shabestari
    TO : Vladimir Nelyubin
    3rd : Juan Carlos Cornejo


    16:00 Shift started. No beam.

    17:00 Moved target to empty.

    17:45 Yi asked MCC for raster off.

    ~19:30 MCC started unning the beam

    19:45 BigBite HV tripped

    ~19:50 RICH HV tripped during beam tunning

    20:00 BigBite HV tripped again. MCC is trying to tune the beam.
    Will keep the HV off till we get stable beam.

    20:05 Turned the RICH HV off. Will turn it back on ater getting stable beam.

    MCC called. They are trying to tune the beam. We got beam for couple of minutes, so I asked for raster on. However, they have optics problem, which doesn't allow them to give us 2uA beam nor Harp scan.


    No production data for swing shift.