    keyword=swapped TS2 module with spare

    I swapped the TS2 (trigger supervisor) module with the spare one in the bigbite weldment. I did some tests with both pulser and random rate on T3 with different prescales and could not reproduce the problem of negative deadtime that we saw last night. At least the dead time make sense if I compare roughly the CODA rate, prescale factors and raw rate. I think it will work.

    I have the bad TS2 module surveyed and will take it to Ed( from DAQ group) to fix this so that it will serve as spare.